Good morning. The Senate passed its permitting package, Meta's emissions jumped 45% and SPP approved $23.7 billion of transmission.

Top Stories

SENATE SENDS ITS PERMITTING PACKAGE TO THE HOUSE 62-33
Associated Press
The bill would shorten reviews for power plants, transmission lines and other energy infrastructure while requiring data centers to cover their power costs. The House passed a narrower version in 2025.

ENTERGY'S META PLANT COST JUMPS 63% BEFORE SEVEN MORE REQUESTS
WWNO
Waterford 5 is now projected at $1.755 billion, up $676 million from its original estimate. Entergy is expected to seek approval in December 2026 for seven more gas plants and related transmission.

SPP APPROVES A $23.7 BILLION TRANSMISSION PLAN
RTO Insider
The grid operator's board and Members Committee approved the 2026 buildout, including six additional 765-kV lines.

OHIO APPROVES 2.15 GW OF GAS PLANTS FOR DATA CENTERS
Signal Cleveland
An 800-MW plant would serve EdgeConneX, while a 1,350-MW project would supply Vantage's $2.1 billion campus. Both still need separate environmental permits.

META'S AI BOOM PUSHES EMISSIONS UP 45%
Bloomberg
Meta's net emissions reached 11.8 million metric tons in 2025 as electricity use rose 35%. The company is re-evaluating the 2030 deadline for its net-zero goal.

Power & Grid

NEW YORK SHORTLISTS 10 NUCLEAR DEVELOPERS FOR A 5-GW BUILDOUT
Engineering News-Record
NYPA selected 10 finalists from 21 applicants. It expects to choose a site and technology for the first 1 GW in the first half of 2027.

NEW YORK SEES ITS FIRST STATEWIDE CAPACITY SHORTFALL IN 2033
Utility Dive
NYISO projects a 225-MW deficit that grows beyond 1,850 MW by 2036. Its forecast includes 1,700 MW of new data-center demand and 1,000 MW of manufacturing load.

ANTITRUST SUIT CHALLENGES A $1.6 BILLION CALIFORNIA LINE
San Diego Union-Tribune
Plaintiffs say CAISO and SDG&E shifted the 500-kV project from a roughly $1 billion competing bid before a new substation. The complaint asks a court to void the contract.

AMEREN PROPOSES A 2.1-GW MISSOURI GAS PLANT
Alton Telegraph
Three combined-cycle units beside the Sioux Energy Center would be built from 2027 through 2031. The project still needs Missouri regulators' approval.

ARIZONA APPROVES A MIXED GAS, SOLAR AND BATTERY PLANT
KJZZ
SRP's Marigold project won state approval in Pinal County. Residents and advocates raised air-quality and water concerns about the site.

Data Centers

ROANOKE ASKS VIRGINIA FOR A TWO-YEAR DATA-CENTER PAUSE
Cardinal News
The city council added a statewide moratorium to its legislative wish list. At least three moratorium bills have already been filed in the General Assembly.

MIT MODEL TIES DATA-CENTER POWER POLLUTION TO 650 PREMATURE DEATHS
Phys.org
The peer-reviewed model attributes 513 deaths to added fine-particle pollution and 137 to smog in 2023. The total equals 5.3% of modeled electricity-related mortality.

TESLA SEEKS TAX BREAKS FOR A PROPOSED $3.1 BILLION POLYSILICON PLANT
pv magazine
Tesla says the Nueces County project is under consideration and contingent on tax relief. Construction would run from 2027 through 2030 if approvals are secured.

DATA-CENTER CANCELLATIONS MORE THAN DOUBLED IN THE THIRD QUARTER
ESG Dive
Relae counted 16 stopped U.S. projects, up from seven in the third quarter of 2025. Its tracker combines formal denials, zoning bans and developer withdrawals.

GOOGLE OFFERS $10.8 MILLION TO SPEED AN OHIO GRID UPGRADE
Columbus Dispatch
The proposal would reconductor 15.5 miles, deliver Google's contracted 24 MW about two years early and eventually unlock more than 700 MW. State approvals remain pending.

Stat of the Day

4,600 MW

New York fossil generation that will be more than 70 years old by 2036
NYISO models 2,600 MW of that fleet as unavailable.
Utility Dive ↗